Rare Element Resources Completes Trenching Program with Assays Indicating Bulk Sample Average Grade of 10.1% Total Rare Earth Oxide

by User Not Found | Nov 06, 2014
Rare Element completes trenching program, with average grade along strike of 10.1% total rare earth oxide, and excavates 1000 ton sample for use in large-scale demonstration plant.

1,000 Tons of Trench Material Excavated for Use in Planned Large-Scale Demonstration Plant

November 6, 2014 – Lakewood, Colorado - Rare Element Resources Ltd. (the “Company”) (NYSE MKT: REE and TSX: RES), a mineral resource company advancing development of the Bear Lodge Critical Rare Earth Project (the “Project”) located in northeast Wyoming, announced today that it has completed a trenching program that confirmed geology, structure and grade of the near-surface, high-grade zone at the Bull Hill deposit. Additional studies are underway to confirm detailed mineralogy. The trenched area is the anticipated site of initial mining as contemplated in the recently released Preliminary Feasibility Study (PFS).  Bulk samples excavated during the trenching returned average assays of 10.1% total rare earth oxide (TREO) over a length of approximately 225 feet (69 meters). Approximately 1,000 tons (907 tonnes) of mineralized material were excavated from the trench to feed a planned demonstration-scale plant using the process flowsheet that incorporates the Company’s proprietary recovery technology, including the recently announced process for the production of partially separated rare earth products.  

“The results of the trenching and bulk sample program were positive on multiple levels,” said Jaye T. Pickarts, Chief Operating Officer.  “We were able to confirm the continuity, orientation and grade of the high-grade zone in that portion of the ore body we intend to mine first.  This work allowed us to collect valuable data that will be incorporated into detailed engineering.  Most importantly, we excavated a large mineralized sample that we plan to use in a demonstration plant to confirm on a larger scale our process flow sheet, including the recently announced separation technology.  It will allow us to thoroughly evaluate and confirm the entire process, from run-of-mine to the creation of a significant quantity of final, separated products on a continuous-run basis.  This work will generate important information that will contribute to both the Feasibility Study and detailed engineering, including testing materials of construction, confirming equipment selection, and verifying material handling parameters. Having this information prior to construction should de-risk the project significantly and greatly reduce or eliminate the numerous start-up issues experienced by other companies in the rare earth sector.”

The trench exposed the Bull Hill main dike for a total distance of approximately 300 feet (91.4 meters) along a northwesterly strike with widths that varied from 8 to 20 feet (2.5 to 6.1 meters).  Nine 120-ton bulk samples were collected on 25-foot spacing (7.6 meters), with 2-ton (0.9 tonnes) representative sub-samples collected from each block for preliminary metallurgical testing.  Nine 30-pound (13.6 kg) representative assay samples were collected from each sub-sample to provide an estimate of grade and continuity. These assays range from 3.65% to 14.65% TREO and average 10.1% TREO.  Four cross trenches were excavated and sampled (six 12-ton bulk samples, each with a 0.5 ton sub-sample and an assay sample) to provide material to test the processing character of mid- to low-grade stockwork material and help ascertain the trend and character of the dike and adjacent stockwork zones.      

The excavation confirmed that the main, highly oxidized carbonatite dike at the Bull Hill deposit is flanked by parallel dikes, splays and stockwork mineralization collectively forming a mineralized zone that extends at least 300 feet (91.4 meters) along strike and attains widths of up to 40 feet (12.2 meters).  In the subsurface, this zone expands to more than 300 feet (91.4 meters) in width, based on detailed drilling and assay data.  Geological information collected from the trench proves dike orientation and continuity, mineralogy and grade along its northwest strike.  Structural mapping data collected validates trends utilized in resource modeling and will be incorporated in pit wall stability design.

The 1,000-ton bulk sample collected from the trench is currently being stockpiled on Company-owned property at the Bear Lodge Project.  The area of excavation has been reclaimed in accordance with U.S. Forest Service and Wyoming Department of Environmental Quality standards.

Planned Demonstration Plant

Pending financing and the successful completion of additional bench-scale testing of the Company’s recently announced separation technology, the Company plans to construct in 2015 and then operate a larger-scale (1 - 3 tons per day), continuous-run demonstration plant to confirm its process flow sheet from physical upgrade to separated rare earth oxide products.  It anticipates generating approximately 70 tons (63 tonnes) of rare earth products from processing the trench material, based on expected recovery rates.  The demonstration plant will contribute important operating data for consideration in the planned Feasibility Study and inclusion in detailed engineering, with the goal of avoiding some of the startup issues that have plagued others in the rare earth sector.  Additionally, the resultant products will be provided to a wider range of potential offtake partners for evaluation and testing for specific applications.  

Rare Element Resources Ltd. is a publicly traded mineral resource company focused on exploration and development of rare-earth element deposits, specifically those with significant distribution of critical rare earths.  The Company is advancing development of the Bear Lodge Project, located in northeast Wyoming.  Bear Lodge is a significant mineralized district containing many of the less common, more valuable critical rare earths that are essential for electronics, fiber optics, laser systems for health and defense, as well as many evolving green technologies, like hybrid cars, solar panels and wind turbines. Permitting and feasibility work on the Project continue to advance.  The Company is a member of the U.S. Department of Energy’s Critical Materials Institute, a combined government and private sector organization committed to eliminating supply chain issues for rare earths and other critical elements.  Please see CMI’s website at https://cmi.ameslab.gov/ for additional details on its mission and members.

For additional information, please visit the Company’s website at www.rareelementresources.com or contact Robbin Lee at 720-278-2462 or rlee@rareelementresources.com.

John T. Ray, MS, Rare Element’s internal, qualified person under Canadian NI 43-101, supervised the preparation of the scientific and technical information concerning the Company’s mineral project contained in this new release. 

Forward Looking Statements

This news release contains forward-looking statements within the meaning of securities legislation in the United States and Canada. Except for statements of historical fact, certain information contained herein constitutes forward-looking statements. Forward-looking statements are usually identified by our use of certain terminology, including "will", "believes", "may", "expects", "should", "seeks", "anticipates", "plans", "has potential to", or "intends" (including negative or grammatical variations thereof) or by discussions of strategy or intentions. Such forward-looking statements include statements regarding: the plan to construct, operate, timing and ability to finance a demonstration-scale plant and the expected results and benefits thereof, the estimated impacts to the final Project from the demonstration-scale plant; the trenching program results and impact on the ultimate resource estimate; the timing and expected results of a definitive Feasibility Study including the potential for upside as a results of the incorporation of Project opportunities into the definitive Feasibility Study; processing test work and expected results; permitting process and progress; the expected commissioning of the Project and Project development plans for the future. Such forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause our actual results or achievements to be materially different from any future results or achievements expressed or implied by such forward-looking statements.

Factors that could cause actual results to differ materially include, but are not limited to, the progress of our Bear Lodge Project; estimated Project economics and parameters from the PFS, fluctuations in demand for, and price of, rare earth products; success of process technology under testing or development; results from geological evaluations and programs; timing of and unexpected events at the Bear Lodge property; delay or failure to receive government approvals and permits; our ability to obtain financing for the Project on acceptable terms or at all; changes in U.S. and Canadian securities markets; and general economic conditions. There can be no assurance that future developments affecting the Company will be those anticipated by management. Please refer to the discussion of these and other factors in our Annual Report on Form 10-K for the year ended December 31, 2013. We expect that the above estimates as to development plans, technology and other processes, time frames and financial needs will change as new information is received and that actual results will vary from these estimates, possibly by material amounts. While we may elect to update these estimates at any time, we do not undertake to update any estimate at any particular time or in response to any particular event. Investors and others should not assume that any forecasts in this news release represent management's estimate as of any date other than the date of this news release.

Leave a comment


Rare Element Resources
Fact Sheet

Thumbnail 2 24


Rare Element Resources
Technology Fact Sheet

Thumbnail 2 24

Most Recent Presentation
The MoneyShow Orlando

October 30, 2023

Money Show Orlando - October 2023

Technical Report Summary on Bear Lodge REE Project

Updated Mineral Resource for Bear Lodge Focused on Key Magnet Materials


Picture3


Open House – October 09, 2023

State and community leaders joined Senator Barrasso, Neal Blue and Brent Berg with the ceremonial groundbreaking shovel

Ceremonial groundbreaking with Senator Barrasso, state and community leaders, Neal Blue (GA) and Brent Berg (RER) 

The Company and General Atomics (GA), supported by state and community leaders, celebrated a ceremonial groundbreaking for their rare earth demonstration plant.

The presentation at the Open House made by Mr. Berg can be found here.

For a summary of the event, please click here.

Please click here to see a video replay from the Newcastle News Letter Journal of the event.

CEO Corner

Commentary from Kelli Kast,
Interim President, CEO and Director

Continuing Our Progress

As I step into the role of Interim President and Chief Executive Officer (“CEO”) for the coming weeks, I do so with confidence that we will seamlessly continue on the path the Board has set for us of progressing construction of the demonstration plant toward operations this summer, and in continuing to build awareness of the Company, the Bear Lodge Project, and the importance of establishing a secure domestic rare earth supply chain.

Please click here to read full content

Please click here to see appointed President and CEO Ken Mushinski's bio

Demo Plant Construction Update (4/9/24)

Interior Improvements at the Upton plant site

Interior Work Preparing for Skids


Utilities upgrades at the Upton site are mostly complete. Building renovations are progressing in preparation for the arrival of the first skid of processing equipment, expected in late April, with others to follow throughout the month of May.

World-Class Technology Partner

General Atomics Fact Sheet
In 2017, an affiliate of General Atomics, one of the largest, most advanced technology companies in the world, took an equity position in Rare Element Resources.  Since that time, they have brought the full force of their technology development team enhance the Company's recovery/separation technology.
To learn more about General Atomics Click Here

Bear Lodge Panoramic
Sample Drilling
Core Samples

The Bear Lodge Project area is a significant mineralized district that contains one of the largest disseminated rare earth deposits in North America. This deposit contains many of the less common, more valuable rare earths that are essential for the magnet materials used in electronics, fiber optics, laser systems for health and defense, and many evolving green technologies, such as hybrid cars, solar panels and wind turbines. Rare Element Resources owns 100% of the Project. 

During the last few years, the Company, along General Atomics, whose affiliate is RER's majority shareholder, have been advancing their proprietary extraction/separation technology and have successfully produced commercial-grade neodymium/praseodymium (Nd/Pr) oxide in pilot-plant testing.  These materials are key components to the fast-growing, permanent magnet sector. The next step will be operations of a demonstration plant, which is currently under construction in Upton, WY.  Results generated from operating this plant will be used for the design and economic evaluation of a commercial rare earth processing facility. 

Project Highlights

  • Proprietary Rare Earth Extraction/Separation Technology – Successfully advanced the Company’s technology and produced neodymium/praseodymium (Nd/Pr) oxide in pilot-plant testing. Construction of a demonstration plant is currently underway to prove the scalability of the process and define the requirements for a commercial plant.
  • World-Class Technology Partner and Majority Shareholder – General Atomics, through its affiliate, is the majority shareholder in Rare Element Resources, is a technology leader with a proven track record of bringing new ideas to market.  Their understanding of the strategic role rare earths play in numerous advancing technologies makes them keenly aware of the need for a secure, domestic supply of rare earths. Their relationship within the U.S. Government have been essential to our ability to advance our technology.
  • Bear Lodge Project – Well-defined resource with excellent concentrations of the rare earth elements essential to high-strength, permanent magnets and the many industries that depend on them.  Two of those industries, electric vehicles and wind turbines, are expected to drive a doubling of demand for magnet materials in the next 10 years.
  • Strategic Location – Located in northeast Wyoming, the Bear Lodge Project has easy access to a major interstate, transcontinental rail, natural gas and low-power.  The area has existing infrastructure with a ready and skilled workforce.  The State of Wyoming has a rich history of mineral development and a pro-business focus, and its leaders are actively committed to economic diversification. 
  • Strong Federal and State Support – Both the Department of Energy (DOE) and the Wyoming Energy Authority (WEA) have shown their support for the Project through funding of over $26M for the demonstration plant.  The DOE continues to pursue ways to secure sources for material that will be key to industrial needs, especially those that support the country’s initiative of reducing carbon emissions, like electric vehicles and wind turbines. The WEA is supporting the State’s desire to diversify employment and understands that Wyoming can play a key role in developing a domestic supply chain – from minerals to magnets. 